Project Resourcing
Home > Project Manager > Project Resourcing | Index |
IntroductionProject Resourcing allows those users that are allocated the Project Portfolio Manager role to view the workloads and define the capacity of both individual stakeholders and project teams. |
Related Articles |
Stakeholders
-
The stakeholders tab displays a list of Project Manager users and provides a choice of three views for the selected stakeholder. The first and default view is called the '2 Week Workload' view and displays project tasks assigned to the selected stakeholder in the form of a gantt chart. The second view is of Project Tasks assigned to the selected stakeholder, and the third view is of Projects the stakeholder is a member of.
-
The stakeholders tab displays a list of Project Manager users and provides a choice of three views for the selected stakeholder. The first and default view is called the '2 Week Workload' view and displays project tasks assigned to the selected stakeholder in the form of a gantt chart. The second view is of Project Tasks assigned to the selected stakeholder, and the third view is of Projects the stakeholder is a member of.