Difference between revisions of "Approving, Scheduling, and Implementing Changes"

From Hornbill
Jump to navigation Jump to search
Line 9: Line 9:
 
==Approvals==
 
==Approvals==
  
== Scheduling==
+
==Scheduling==
 +
 
 +
Changes can be scheduled manually using the '''Schedule''' action bar option on the Change record. Using the business process engine, the underlying Change process can be '''suspended pending scheduling''' which will take the Change record in context to the '''Schedule''' action option, and will wait for the Change to be scheduled before the Change process resumes.
 +
 
 +
Once a Change is scheduled it will appear on the Forward Schedule of Change calendar.
 +
 
 +
===Forward Schedule of Calendar===
  
 
In ''Service Manager''  if you have at least the ''Change Calendar Viewer'' role, you can review scheduled change in the change calendar by:-
 
In ''Service Manager''  if you have at least the ''Change Calendar Viewer'' role, you can review scheduled change in the change calendar by:-
 
:# On the [[What_is_the_Navigation_bar? |navigation bar]] select Service Desk [[File:Service_Desk.png |16px| Service Desk]] and then 'Change calendar'
 
:# On the [[What_is_the_Navigation_bar? |navigation bar]] select Service Desk [[File:Service_Desk.png |16px| Service Desk]] and then 'Change calendar'
:# This displays the current month. Today’s date is highlighted along with any changes scheduled by day
+
:# The default view is the current month. Today’s date is highlighted along with any changes scheduled by day
:# Each change can be reviewed by selecting it
+
:# Each change can be reviewed by selecting it and drilling down into the change record.
 
:# You can change the view to by week or day and scroll between those periods using the ‘<’ or ’>’ buttons
 
:# You can change the view to by week or day and scroll between those periods using the ‘<’ or ’>’ buttons
  
  
 
[[Category: Service Manager]]
 
[[Category: Service Manager]]

Revision as of 19:53, 7 December 2015

Home > Service Manager > Approving, Scheduling and Implementing Changes

Introduction

Once a Change has been assessed and accepted it may require a prescribed business process to be followed which may involve approvals, scheduling, and tasks. All of this can be orchestrated using the Business Process Engine. The complexity of the underlying change process can be shielded from the change users, and instead a graphical Head's Up Display can represent the Processes stages, tasks, authorisations, and milestones.

Change Process.png

Approvals

Scheduling

Changes can be scheduled manually using the Schedule action bar option on the Change record. Using the business process engine, the underlying Change process can be suspended pending scheduling which will take the Change record in context to the Schedule action option, and will wait for the Change to be scheduled before the Change process resumes.

Once a Change is scheduled it will appear on the Forward Schedule of Change calendar.

Forward Schedule of Calendar

In Service Manager if you have at least the Change Calendar Viewer role, you can review scheduled change in the change calendar by:-

  1. On the navigation bar select Service Desk Service Desk and then 'Change calendar'
  2. The default view is the current month. Today’s date is highlighted along with any changes scheduled by day
  3. Each change can be reviewed by selecting it and drilling down into the change record.
  4. You can change the view to by week or day and scroll between those periods using the ‘<’ or ’>’ buttons